Laser & MC

14 Sep.,1998


Recent Schedule

(11 Dec.,1998)
Task Preparation Charge
Dec. Frequency stabilizaion(NPRO) Circuits of Servo Nagano
Alignment control(Setup) Quadrant PD Telada, Sekiya
Jan. Frequency stabilizaion(10W) Nagano
Alignment control(Experiment) Circuits of Servo Telada, Sekiya
Feb. Installation of Magnets for I/O mirrors Magnets&Stand off Telada, Sekiya
Installation of Steering Block Steering Block Takahashi, Nagano
Connection of MC and RM Gate valve& Bellows Takahashi, Fukushima
Alignment&Matching to Arm Nagano